Client Assurance CDM Project

Scope:

Inspect a STOR project for compliance during Construction Phase RIBA Stage 5

Work completed:

1 day spent on site with management teams and operatives;
1 day writing report and client feedback

Outcome:

Red Amber Green audit report created
Feedback to site management and operatives provided on site
Revision in working at height practices implemented immediately
Increased understanding of COSHH storage requirements
Assurance that client had engaged competent principal contractors for the commission
Further consultancy services with the client secured

☎ +44 (0) 7572 877 551

- June 2017 View
This testimonial was successfuly verified by other source.

Health and Safety PQQ (Strategic piece)

Scope:

Review existing PQQ process and recommend improvement for safety and health performance criteria.

Work completed:

1 day spent on site with management teams and operatives;
1 day writing report and client feedback

Outcome:

Enhanced the objective measuring of the client PQQ to ensure consistency
Recommendations for interview techniques applied
Increased due diligence process of the PQQ and introduced Minimum Levels of Performance

☎ +44 (0) 7572 877 551

- June 2017 View
This testimonial was successfuly verified by other source.

Accident | Incident Investigation

Scope:

Review a client contractor safety processes following a reported incident during a utility service excavation and connection project.

Work completed:

1 day spent on site with management teams and operatives;
1 day writing report and client feedback

Outcome:

Root Cause Analysis completed and areas to improve identified
Recommendation that contractor apply revised controls post-incident
External audit of contractor provided insight into a positive safety and health culture

☎ +44 (0) 7572 877 551

- June 2017 View
This testimonial was successfuly verified by other source.

Residential CDM Project

Scope:

Review a residential build scheme with 12nos. 3 bedroom houses and 3nos. 2 bedroom houses. Assess suitability of design and record significant risks.

Work completed:

1 day spent with designers of the scheme to understand the objectives and criteria for planning;
1 day writing report
½ day presenting report to the project management team

Outcome:

Designed out traffic risk to completed scheme by adding a low-level kidney roundabout
Added an additional greenspace to the rear of existing plots by 4m2
Added an additional 2 nos. 2 bedroom properties to the scheme using the same footprint
Increased value of the project by £65,000 net.

☎ +44 (0) 7572 877 551

- June 2017 View
This testimonial was successfuly verified by other source.

    Find the right professionals in Manchester

    View The Full Index

    Search By:

    Submit your Enquiry here

    Enquiry Details

    Contact Details